Setting Priorities for Concurrent Replications

Prev Next

You can schedule multiple replications to run at the same time because each replication runs as a separate thread. You can also assign a priority to each replication from the Replication Properties dialog.

  1. In the Management Center Metadata Explorer, select the replication.

  2. From the right mouse button menu, choose Replication Properties.

  3. In the Replication Properties dialog, go to the Preferences tab.

  4. In the Thread Priority field, click the down arrow to display a list of priorities.

  5. Select the appropriate priority for the replication.

  6. Click OK to close the Replication Properties dialog.

Related Topics
Managing Multiple Concurrent Replications

Creating a Replication Group

Defining Multiple Table Replications